Eyeing completion by February 2027: MMRDA speeds up work on Atal Setu–Mumbai-Pune Expressway connector
India

Eyeing completion by February 2027: MMRDA speeds up work on Atal Setu–Mumbai-Pune Expressway connector

Indian Express·2h ago·Neutral

What Happened

MMRDA has accelerated construction on the 7.35-km Atal Setu–Mumbai-Pune Expressway connector, targeting February 2027 completion. Foundation work completed at 143 of 176 locations; 141 piers constructed with 88 fitted with caps. The six-lane elevated corridor will provide signal-free access between Atal Setu and Mumbai-Pune Expressway via Navi Mumbai, benefiting commuters and the upcoming Navi Mumbai International Airport.

Key Entities

MMRDAAtal SetuMumbai-Pune ExpresswayNavi MumbaiNavi Mumbai International AirportChirlePalaspeSanjay Mukherji